Miramar dummy build — Quality Daily Status Report — Day 16 (2026-11-13)
=================
Data cut-off: 2026-11-13 14:00 (VN) Phase: dummy build
OVERALL STATUS: RED
- EXECUTIVE SUMMARY
- Containment: All 4,820 pcs of AMPB shield plate lot SG-2607 under 100% quarantine in VN and CQ; no unit has left the line since 2026-11-12 09:40.
- Build and lines: DVT build Day 16: 2 FATP lines and 1 auto SMT line; the AMPB station is stopped, MLB keeps running.
- OBA post-seal 27/27 passed; no new finding from the factory team.
- OK2Ship: OK2Ship still planned for 2026-12-05; the blocker below is the only open risk to that date.
- 8D / CAPA: 8D opened on 2026-11-12, containment section submitted; full report due 2026-11-20.
- FACTORY DATA (cut off 2026-11-13 14:00 (VN))
OBA:- Pre-seal: Cum. inspected 1,956 (▲ +44) pcs, passed 1,956 (▲ +44) pcs, pass rate: 100.00%.
- Post-seal: Cum. inspected 27 pcs, passed 27 pcs, pass rate: 100.00%.
SMT MLB Production Data: - Cumulative actual Input/Output: 31,480 / 31,436 (▲ +1,232) pcs. Cum. FPY: 99.86% vs target: 98.50%, Cum. RPY: 99.94% (▲ +0.1 pp).
- Daily actual Input/Output: 1,232 / 1,229 (▼ -36) pcs. Daily FPY: 99.76% vs target: 98.50%.
SMT AMPB Production Data: - Cumulative actual Input/Output: 12,000 / 11,814 (▼ -1,400) pcs. Cum. FPY: 98.45% vs target: 98.50% (▼ -1.2 pp), Cum. RPY: 99.12% (▼ -0.5 pp).
- Daily actual Input/Output: 500 / 468 (▼ -110) pcs. Daily FPY: 93.60% vs target: 98.50% (▼ -5.9 pp).
FATP Production Data: - Cumulative actual Input/Output: 15,210 / 15,010 pcs. Cum. FPY: 98.69% vs target: 97.50% (▼ -0.3 pp), Cum. RPY: 98.68% (▼ -0.3 pp).
- Daily actual Input/Output: 1,180 / 1,163 (▲ +40) pcs. Daily FPY: 98.56% vs target: 97.50% (▼ -0.7 pp), Daily RPY: 99.81% (▲ +0.5 pp).
- OK2SHIP CRITICAL ISSUE(S) — 1 blocker, 0 critical
Issue 1 : MIR-1042 — [Assembly] AMPB shield plate interferes with FATP test fixture
Level: Blocker Risk: Red- Status: On-going DRI: Henry Zeng JIRA Ticket(s): MIR-1042
- Description: During DVT FATP assembly in VN on 2026-11-12, the AMPB shield plate fouled the RF test fixture on 32 of 500 units; the line was stopped at 09:40 and the affected lot quarantined.
- Customer Failure Mode: Shield plate sits 0.4 mm proud of the housing; the fixture cannot seat and the unit cannot be tested, so the station jams.
- Failure Analysis: Cross-checked 5 failing and 5 passing units: the gap follows the AMPB shield plate lot, not the fixture. Supplier SG-2607 measured 0.42 mm above nominal on 3 of 3 sampled plates.
- Root Cause / Leading Hypothesis: Leading hypothesis, not yet proven: a worn stamping die at the supplier drove the plate above the upper tolerance from 2026-11-05 onward.
- Containment Action(s): 4,820 pcs of lot SG-2607 quarantined in VN and CQ; 100% gap check added at incoming and at the FATP station; 32 suspect units segregated for teardown.
- Corrective Action(s): Supplier to re-stamp lot SG-2607 with a verified die; replacement material to VN with ETA 2026-11-19; die measurement report requested.
- Preventive Action(s): Die wear counter and a first-article gap check at each supplier lot start; lot SG-2607 traced end to end.
- Next Steps & Dates: Die measurement report from supplier - DRI Henry Zeng - ETA 2026-11-15. Replacement material to VN - DRI Henry Zeng - ETA 2026-11-19.
- Factory Risk Assessment: Line-stop risk on AMPB from 2026-11-17 if the replacement material slips; MLB is not affected.
- Field Exposure Risk Assessment: No unit with lot SG-2607 has shipped to a customer.