Home / Pages / Miramar · Miramar DVT · DVT — Stage build report

Miramar · Miramar DVT · DVT — Stage build report

Amara 2026-11-21 22:11 Filed in Miramar Page
Version 60 of 60

Data cut-off: 2026-11-21 14:00 (VN) · Phase: DVT

OVERALL STATUS: RED

1. Overall status and executive summary

Overall quality status is Yellow. FATP yield remains below the 97.5% target, with the primary loss at ACT.

  • MDF-2 Line-stop Issue: The uneven height of the IO Jack seat prevents the IO heatsink from locating properly, so the screws cannot be fastened, which stops the line.
  • Build and lines: 1 Auto line is active and is certified by line audit.
  • Pre-CET: Pre-CET is scheduled for testing on 12/5, and the test report should be ready by 12/9.

2. Factory data ( Main Build) cut off 2026-11-21 14:00 (VN)

OBA

  • Pre-seal: Cum. inspected 21 pcs, passed 0 pcs, pass rate: 0.00%.
  • Post-seal: No main build unit input as of data cut-off.
  • There are 11 SW issues still open right now (1 new catches on DVT and 10 known SW issues).

SMT MLB Production Data

  • Cumulative actual Input/Output: 2,995 / 2,947 pcs. Cum. FPY: 99.62% vs target: 98.50%, Cum. RPY: 99.70%.

SMT AMPB Production Data

  • Cumulative actual Input/Output: 3,639 / 3,159 pcs. Cum. FPY: 100.00% vs target: 98.50%, Cum. RPY: 100.00%.

FATP Production Data

  • Cumulative actual Input/Output: 442 / 43 pcs. Cum. FPY: 84.13% vs target: 97.50%, Cum. RPY: 97.39%.

3. DVT highlight issues — 0 blocker, 1 critical

Issue 1 : MIRAMAR-1880 — Horizontal convergence angle failure found at ACT

  • Level: Critical · Risk: YELLOW
  • Status: Resolved · DRI: Ethan Su (Huaqin) · JIRA Ticket(s): MIRAMAR-1880
  • Description: Horizontal convergence angle failure found at ACT
  • Customer Failure Mode: Camera captures show visible tilt/distortion in images.
  • Failure Analysis: Phenomenon: Horizontal convergence angle measured 4.15 vs spec [-3,+3]; test image shows camera tilt; teardown mechanism: camera rubber cover severely tilted and pressed by mic bracket, causing significant rightward camera tilt. LCM not misaligned and gap/step within spec; reassembly with rubber repositioned and mic bracket removed passes ACT.
    • GVW62R016455009A
    • 2 GVW62S0064660088
    • GVW62R01645500E5
    • Current Jira failure rate: 1.02% [3/295].
  • Root Cause / Leading Hypothesis: Mechanical assembly defect: camera rubber cover severely tilted and pressed by the mic bracket, causing camera optical axis misalignment and rightward camera tilt; LCM and gap/step measurements were within spec, and reassembly with proper rubber positioning/mic bracket clearance passed.
  • Containment Action(s): Emphasize operator thoroughness during camera and rubber installation at FATP station.
  • Corrective Action(s): Proposed permanent fix: change camera protective film to transparent material so operators can more easily verify camera rubber position.
  • Preventive Action(s): Add FATP visual inspection/work-instruction check for camera rubber seating under transparent protective film and verify mic bracket clearance to prevent pressing the camera rubber cover.
  • Next Steps & Dates: Validate transparent camera protective film change and update FATP inspection work instruction
    • Evaluate mic bracket clearance/assembly design to prevent pressing the camera rubber cover
    • Complete FA on all affected SNs and confirm failure mechanism repeatability
    • Monitor ACT horizontal convergence angle failure rate and implement 100% sorting/hold if rate increases
  • Factory Risk Assessment: Moderate: Jira failure rate is 1.02% [3/295] at ACT, and containment currently relies on operator thoroughness re-emphasis;
  • Field Exposure Risk Assessment: Low if all units undergo ACT horizontal convergence angle screening prior to shipment; escaped units could show tilted/distorted camera images showing as ACT failure.