The levels, the fields and the sources this daily report follows.Customization

0 · Five real reports

The archived HQ PQA mail thread is not on this PC, so the example pages cannot be rebuilt. They are generated from 02_Training\PVT Experience\From HQ PQA - Product A PVT Quality Daily Status Report - Day 17.mht.

Sources — the originals, one click away

Every rule on this page comes from one of these files. They are archived in /app/rules/xbuild/00. Inspiration/01. References so nothing depends on a folder outside the programme. Press Open and the file opens in the desk's own reader.

SourceFile
PDP Milestone Document Guidelines for ULE Programs v1
The issue format, the Red / Yellow / Green code and where each level sits in the deck.
PDP Milestone Document Guidelines (OK2Ship issue format).md
missing from the archive
Jira Bug Compliance Standard
The PDP field matrix per level, the update cadence and the colour-mismatch alerts.
Jira Bug Compliance Standard.md
missing from the archive
PVT course 5 — Preparing the PVT Daily Report
The four sections, where every number comes from, and what makes an issue critical.
course-05-daily-report.md
missing from the archive
PVT course 2 — The Daily Rhythm
The two meetings and who is in the room.
course-02-daily-rhythm.md
missing from the archive
Product A PVT Quality Daily Status Report — Day 6 to Day 17
Eight real reports in one mail thread: the shape the accepted report takes.
Product A PVT Quality Daily Status Report - Day 6-17 (whole thread).md
missing from the archive
Product A thread — the original .mht
The untouched Outlook export the example pages are built from.
From HQ PQA - Product A PVT Quality Daily Status Report - Day 17.mht
missing from the archive

1 · The four levels, and the one test that decides between them

Three questions, asked in this order: is the root cause identified, can the solution land inside POR, and is the validation large enough to believe? The answers set the level. Nothing else does.

LevelCriteria FieldsUpdate cadence Sits in the deck
Blocker
Red
Root cause not identified, or there is no solution / the fix cannot land inside POR, or validation is incomplete or holds on a small sample only. Applies from DVT RR through OK2Ship. A White Paper review is required.8 required + 3 optionalEvery 1 dayTop Issue section
Critical
Red (not a blocker) or Yellow
Root cause identified, solution can land inside POR, but validation is still incomplete or small-sample. Typical at HVT / EVT RR.8 required + 3 optionalEvery 3 daysTop Issue / x-Functional
Major
Yellow
Root cause identified and the fix fits inside POR; no product-wide exposure.5 requiredEvery 3 daysx-Functional section
Minor
Green
Fully validated on a large sample. No action needed beyond monitoring.4 required—x-Functional section
The line between Blocker and Critical is validation, not severity. Both are Red when the root cause is unknown. A Blocker stays a Blocker while the fix is unvalidated on a large sample or the root cause is still a hypothesis; a Critical has a real fix inside POR and only the proof is thin.

2 · Does the issue belong in the report at all?

Course 5 of the PVT training: answer yes to any one of these and it is a top-section issue. Answer no to all five and it belongs in a tracker, not in the report.

  1. Does it affect product safety or compliance?
  2. Does it create a customer-visible defect — cosmetic, functional or performance?
  3. Can it stop the line or block shipments?
  4. Does it move yield enough to affect the build plan?
  5. Does it need leadership attention to resolve?
Rule of thumb from the same course: if you would be uncomfortable explaining this issue to a VP, it belongs in the report. Minor, isolated or already-contained issues stay out — they dilute the two or three things that actually need a decision.

3 · What Red, Yellow and Green mean

Colour is the shorthand for the three answers above. It is never decoration — it is the reader's first filter, so a mismatch between colour and facts is the most common audit finding.

ColourRoot causeSolution Validation
RedNOT identifiedNo solution, or cannot be implemented inside PORIncomplete, or only small-sample
YellowIdentifiedCan be implemented inside PORIncomplete, or only small-sample
GreenIdentifiedImplementedFully validated on a large sample

Mismatch alerts worth watching

  • Green, but the validation sample looks small → treat as Yellow until proven on a large sample.
  • Yellow, but the root cause reads "unknown" or "TBD" → it is Red.
  • Red, but root cause is confirmed and the fix validated on a large sample → should be Yellow or Green.
  • Red with no White Paper review reference → violation, required from DVT Readiness through OK2Ship.

4 · Which fields each level must carry

From the PDP Issue Write-up Matrix. A Blocker and a Critical carry the same eight required fields; what separates them is not the paperwork, it is the state of the evidence.

FieldBlockerCritical MajorMinor
Issue DescriptionRequiredRequiredRequiredRequired
Customer Failure ModeRequiredRequired——
Failure AnalysisRequiredRequiredOptional—
Root Cause / Leading HypothesisRequiredRequiredRequiredRequired
Containment Action(s)OptionalOptional——
Corrective Action(s)RequiredRequiredRequiredRequired
Preventive Action(s)OptionalOptional——
Next Steps & DatesRequiredRequiredRequired—
Risk AssessmentOptionalOptional——
DRI(s)RequiredRequiredRequiredRequired
JIRA Ticket(s)RequiredRequiredRecommendedOptional

5 · The 14-field customer format

The OK2Ship top-issue format. This is the version that goes to the customer and to leadership; the daily mail carries the same block with Preventive and the two risk assessments dropped, which makes 12 fields.

  1. Issue / one-line headline
  2. Risk (Red / Yellow / Green)
  3. DRI(s)
  4. JIRA Ticket(s)
  5. Description
  6. Customer Failure Mode
  7. Failure Analysis
  8. Root Cause(s) / Leading Hypothesis
  9. Containment Action(s)
  10. Corrective Action(s)
  11. Preventive Action(s)
  12. Next Steps & Dates
  13. Factory Risk Assessment
  14. Field Exposure Risk Assessment
Writing the description
When, where, exactly what, scope, immediate action taken, measurement data with spec and reading. Example: "FAI466, spec 0.48–0.58 mm, confirmed at the lower specification limit."
Next steps
One line per action: owner (a person, not a team), the action, and a date. Never "ASAP", never "TBD", never "continue investigation".
Root cause
State whether it is confirmed or the leading hypothesis, and whose.
Failure mode
What the end customer experiences if it is not fixed — not the internal defect name.

6 · The four sections of the daily report

The PQA daily quality status report keeps the same shape every day, so a reader knows where each piece of information lives.

  1. Executive summary — overall status, four to seven highlights, readiness-review date, lines and shifts, OBA status, OK2Ship target and data cut-off, FAI done/total, CET sample state.
  2. Factory data — always stamped with the cut-off date and time. OBA pre-seal and post-seal, then SMT and FATP with cumulative and daily input, output, FPY and RPY.
  3. Critical and blocker issues — one block per issue, fields from section 5.
  4. Actions and next steps — owner, action, ETA. Yesterday's actions are either closed or carried forward with an updated status.
Highlight the change. If yesterday was Red and today is still Red, say what kept it Red. A report that repeats yesterday without saying what moved is the one thing readers stop reading.

7 · What the factory numbers mean

TermWhat it is and why it is in the report
OBA pre-seal / post-sealOut-of-box audit before and after sealing. Count of units inspected, units passed and the pass rate. Post-seal is the number the customer reads.
SMT input / output / FPY / RPYSurface-mount line. Input is boards started, output is boards finished, FPY is first-pass yield against the build target, RPY is the rework-pass yield.
FATP input / output / FPY / RPYFinal assembly and test. Same four numbers as SMT, on the finished unit.
CTBCommit-to-build: material committed per configuration. A CTB hold is a line-stop risk, not a quality result.
IQCIncoming quality control. Defects found at the gate, by part number, with quantity — the earliest signal that a lot is wrong.
FAIFirst article inspection. Done / total, with the part numbers approved. A missing FAI blocks the shipment, not the build.
CETCustomer evaluation test / seal aging sample. Sample counts per channel and the report date.
Bonepile / quarantineUnits held out of the line. Quarantine is containment, bonepile is the backlog waiting on failure analysis.

8 · House rules that apply to every report

  • State the data cut-off every time — it tells the reader what could not be in yet.
  • Every number must be traceable. If you cannot say where it came from, do not publish it.
  • Never fill a gap with a guess: write that the source did not state it.
  • One JIRA ID is one issue. Do not split what the source presents as one.
  • Quote failure rates exactly as recorded — "3F/95T", not "about 3%".
  • Never hide bad news. A Red status is information; silence is the failure.

Sources: PDP Milestone Document Guidelines for ULE Programs v1 · Jira Bug Compliance Standard · PVT course 5 — Preparing the PVT Daily Report · PVT course 2 — The Daily Rhythm · the archived Product A PVT Quality Daily Status Report thread, Day 6 to Day 17 · the ULE OK2Ship framework as the Amazon QEM states it (two sessions, one owner per session, a four-day clock that starts on Go).

9 · OK2Ship in ULE — one gate, two sessions

OK2Ship is the quality gate before the product leaves the factory. EMS completes an internal checkpoint five business days before the Amazon OK2Ship meeting and arrives with a formal recommendation and executive sign-off, not with open questions.

How the meeting is built

  1. Session 1 — factory data. EMS populates and presents it, and is fully responsible for it.
  2. Session 2 — internal Amazon. The Amazon section owners present their own sections.
  3. The QEM schedules the meeting and facilitates both sessions. Each section has one single input source — two decks that disagree is the failure mode this removes.
  4. The two sides meet first at the EMS checkpoint (five days before), then the core-team review, then the L7 preflight, and only then at OK2Ship itself.
The QEM focus is customer impact. Customer-impacting issues and the yield concerns that decide FPY come first. Yield issues that sit inside the accepted FPY thresholds are the factory's to manage, and are reported, not escalated.

What EMS brings

  • The internal OK2Ship review, completed five business days before the Amazon meeting.
  • The EMS-owned sections of the deck, filled: customer experience (OBA charts, product audit report, QSG and packaging confirmed to requirements, BOM verification of parts used in the factory), part quality (IQC, LAR, issue resolution and closure), CET results, the reliability summary, compliance where it applies, lessons learned, and factory readiness (yield performance, UPH data, yield bridge, top hitters, bone pile and issue status) for both SMT and FATP.
  • Accessories: every in-box and out-of-box item, confirmed fit, form and function — and where the ownership is Amazon's, what was tested in PVT and when that accessory OK2Ship will complete.
  • SPOR: inputs, qualification status and completion.
  • A formal recommendation — approve, conditional approve, or do not approve — with executive sign-off from EMS quality, engineering and operations, and an overall vote of confidence.
  • The appendix: engineering validation completed with DRI sign-off, P0/P1 validation (hardware only; software P0/P1 that masks a hardware requirement is called out), the PVT product-audit report, BOM verification against the actual BOM, and the ECL report with the percentage match in PVT.
  • Issues found after the checkpoint are fast-tracked: risk assessment and a justification for shipping, communication within four hours, initial failure analysis and root cause within one day. Amazon gives an independent risk assessment on top.

What the QEM brings

  • The meetings: the EMS checkpoint, the Section II core-team meeting, the quality leadership mail or deep dive with the factory where it is needed, the L7/L8 preflight, and the OK2Ship meeting itself, scheduled and facilitated.
  • A review of the EMS deliverables, with a risk assessment and the customer impact stated.
  • PVT device review and feedback where it is asked for.
  • The Amazon-owned sections: PRQ summary, the PVT metrics dashboard, and the critical issue summary with its risk assessment.
  • The approval review meeting, the formal recommendation to leadership, the approval notification to all stakeholders, and the AI follow-up.
  • Lessons learned documented before the sustaining transition.

10 · The deck: who owns each section

Both sessions are reviewed at every meeting. A row belongs to the owner named on it; nobody presents another team's section.

SessionItem Owner
EMS · Section ISupplier vote of confidence, and every risk called outEMS
EMS · Section ICritical issuesEMS — the issue's DRI
EMS · Section ICustomer experience: OBA results and product auditEMS
EMS · Section IPart quality: IQC, LAR, quality issuesEMS
EMS · Section ISMT: yield, issues, burn-down chart, bone pileEMS
EMS · Section IFATP: yield, issues, burn-down chart, bone pileEMS
EMS · Section IReliability, DRDT-ORTEMS
EMS · Section ISPOR — supplier plan of recordEMS
EMS · Section IAccessories, and the copy toolEMS
Amazon · Section IIPVT metricsQEM
Amazon · Section IIComplianceCompliance team
Amazon · Section IIPVT RR actionsSTM
Amazon · Section IICSAT and betaCSAT / Beta PM
Amazon · Section IIBattery shelf lifeAmazon battery DRI, where applicable
Amazon · Section IISoftwareLTPM / SW TPM
Amazon · Section IIPRQ — post-ramp qualificationOPM, pre-aligned with sustaining engineering

The overall summary is Amazon's, with the QEM as DRI; checkpoint readiness is answered at the five-day checkpoint.

11 · The clock: Day 0 to the approval mail

Every date is measured from the data cut-off, and the four-day OK2Ship SLA does not start until the checkpoint answers Go.

WhenEvent OwnerNote
Day 0Data cut-off, daily build meeting, issue resolutionEMSThe daily consolidated report is still sent on the cut-off day.
Cut-off + 1 dayEMS internal OK2Ship checkpoint, with a quality-leadership deep dive on the factory dataEMSFive business days before the Amazon OK2Ship meeting.
Cut-off + 2 daysAmazon OK2Ship core-team reviewQEM / OPMCore-team alignment.
Cut-off + 3 daysAmazon OK2Ship L7 preflight: L7 briefs L8 on the outcomeQEM + EMSL7 leadership review.
Cut-off + 3 daysOK2Ship meeting confirmedQEMThe 72-hour confirmation.
Cut-off + 6 daysAmazon OK2Ship meeting, with the EMS vote of confidenceQEM + EMSThe final approval decision.
OK2Ship + 1 dayFFSQEMQEM mails the field and the ops team.
Three artefacts decide each step: the HQ deck, the Amazon deck and the HQ-plus-Amazon deck. Which one goes to a meeting is fixed by the framework — do not merge them.

12 · What counts as a critical issue at OK2Ship

These are the issue types that must appear in the critical and high-risk section of the review. Each one has a threshold, so "critical" is a fact rather than an opinion.

Issue typeDefinition / threshold
Customer-impacting issueNot effectively contained — it could reach the customer
OBA issueAny hardware or software out-of-box audit finding
RIT escapeCaught at reliability in test but would have escaped to the customer
Line stopA quality-related line stop longer than one day
Major yield issueNTF and real failures above the 1% threshold
Failure modeA mode above the threshold called out in the PVT readiness review
Line verified rejectLVRR above the commodity threshold
Test failureAn OBA / RIT / CET / reliability / compliance failure
Intermittent issueNo identified root cause
Safety and privacyAny safety or privacy risk found during the build
Management approvalAnything that needs explicit sign-off before shipment

13 · Escalation, and how fast an issue has to move

An issue that blocks the build or the schedule is raised in the daily opening meeting by EMS on the day it is found; the QEM decides the path from severity and customer impact.

Leadership is escalated to when

  • Any issue that meets the critical definition and still has no path one day after it was found
  • A line stop longer than 24 hours with no resolution path
  • A yield issue that breaks the FPY requirement by more than 1%
  • Several related issues that together read as one systemic quality problem
  • A schedule risk to the OK2Ship date

Same day

  • A JIRA ticket is created within the same business day the issue is identified.
  • A quality notice goes out, then an update every day until it is closed.
  • Customer impact, severity and next steps are written down.
  • The issue is flagged in the daily hotspot meeting.

Within 24 hours

  • The initial failure analysis, with preliminary findings.
  • A root-cause hypothesis in JIRA, with the supporting data.
  • Containment identified and implemented where customer risk exists.

Within 3 days

  • Closure with a validated root cause.
  • Corrective actions implemented and verified effective.
  • The validation data that confirms the fix recorded in JIRA.
  • Lessons learned captured for knowledge transfer.
Transparency is the rule: no issue is too small to document, bad news travels immediately because delay compounds risk, every update carries evidence rather than speculation, and the whole cross-functional team sees the same picture. Risk is assessed with the GFRPB; the QEM answers questions about it.

What ULE OK2Ship no longer runs

  • No daily build report. Blocker issues go to leadership by email instead.
  • No MIL meeting. If a blocker appears, leadership is asked into the opening meeting for direction; Amazon-owned issues get their own sync.
  • Daily hotspot only while it is needed. A factory issue: the QEM schedules it, EMS runs it and shares the result. An Amazon issue: the QEM facilitates and the issue DRI updates.

14 · The checkpoint answers Go or No Go — nothing in between

  1. Go. The core team or the wider team may proceed to OK2Ship, and the four-day SLA starts immediately.
  2. A list of actions that must be closed inside that four-day window. These do not delay the start; they are the work the window exists for.
  3. No Go. OK2Ship is delayed, which moves the completion date. EMS addresses the blocking concerns and may hold another checkpoint; the four-day SLA cannot start until a Go is given.
A No Go is not a judgment on the programme — it is the gate doing its job before the customer finds the problem.